Walkway to the deck click here...yes another project

Building Our Deck

This venture began in 2024, when we bought the bungalow. Between finding a design we liked, interviewing contractors, and then working our way through the permit process, it became a much bigger undertaking than I had originally imagined.

I will not bore the reader with the multitude of permits, approvals, and variances we had to deal with along the way. Suffice it to say, there was considerably more paperwork involved in building a deck than I ever expected.

I thought it would be worthwhile to include a series of photographs showing the progress of the deck from beginning to end. Looking back, they provide a good record of just how much work went into what, at first, seemed like a relatively simple project.

As a side note, I often wished I had someone like my sister-in-law, Annalea, overseeing the project. With all the paperwork, scheduling, contractors, inspections, and coordination involved, it was certainly outside my normal comfort zone. These are not things I was—or am—in the habit of doing, and having someone with Annalea’s experience handling our “minor little deck project” would have been greatly appreciated.

This is what we had

To get started, the trees you can see in the earlier pictures had to go to make room for the new deck. We used Westwood Tree Service, and they did a fantastic job. Once the trees were removed, however, we quickly realized there was another obstacle—the air-conditioning unit was also sitting directly in the way of our future expanded deck. That would have to be moved as well.

25 Oct 2024

The next step was to find someone to prepare the drawings, and that led us on 25 October 2024 to contact House of Three. They were great people to work with. They came to the house and took detailed measurements, not only outside but inside the house as well, which surprised me at the time. Clearly, there was more involved in designing a deck than I had originally thought.

The pictures below are not House of Three’s final designs. They are simply rough drawings we used during the early planning stages. My sister-in-law, Annalea, also added a few comments and suggestions as our plans continued to evolve.

Originally, we were going to have a full roof over the deck, similar to the one we had at our previous house. Then we scaled that back to a hip roof. Eventually, after looking at all the additional requirements, paperwork, and costs, we decided there would be no roof at all.

It was becoming very clear that our “simple little deck project” was going to be anything but simple. It was going to end up being approximately 450 sq ft.

Permits, Variances—and a Very Important Tree!

As a note, Modest Fencing (our contractor of choice) was instrumental and helpful throughout the design and implementation phases of the project. Roger (the head contractor) has a work ethic that is transmitted to his workers as he not only tackles the job but also helps me (the customer) understand why everything costs what it does. He started in April 2025 working with me.

Once we thought we finally had everything in order, we submitted our application for the necessary permits. That was when we discovered that we also needed approval for a minor variance—at a cost of more than a thousand dollars.

This meant submitting photographs, certified drawings, and all the required documentation to the City. We then had to wait until November 2025, when the committee met to consider our variance request.

The meeting was conducted live on-line, and members of the public were allowed to call in and ask questions about the project. As fate would have it, my new next-door neighbour did exactly that and asked questions about our deck during the live meeting. I have to admit, I was surprised, but by then it seemed to fit perfectly with the way this project was progressing.

In January, while Sharon and I were in Myrtle Beach, we finally received the good news—the variance had been approved.

When we returned home, I went to City Hall thinking that we were finally ready to obtain the building permit. Not quite.

I was informed that I now needed a tree permit. Yes, that meant another few hundred dollars.

The City would not issue the building permit until the Forestry Division inspected the property and confirmed that the tree beside the construction area was being properly protected. For months afterward, people walking past the house would look at all the protection surrounding it and ask me, “What’s so special about that tree?”

Getting the tree permit itself was easy enough—pay the fee . The difficult part was waiting almost two weeks for the inspection of the Tree Protection Zone and then, and only then-receive the tree permit.

By this point, I was beginning to wonder whether we were building a deck or protecting a national treasure.

The Permit That Was Still Missing

Once the Tree Protection Zone finally received the green light from the City, I contacted the Postech representative to arrange installation of the screw-pile foundations for the deck.

Of course, there was one more step.

The original House of Three design called for BigFoot footings, but we had decided to switch to screw piles. Apparently, changing the type of foundation required an engineer to certify the revised design. That meant another few hundred dollars, but by this point I was getting used to hearing that.

With the engineering approval in hand, I hired Postech to install the screw-pile foundations—this time for a cost in the thousands.

Once the piles were installed, I called the City to arrange the required inspection. I thought we were finally moving forward.

That was when I learned something rather important.

Although we had an approved minor variance, the required tree permit, certified drawings, engineering approval, and now the screw piles installed, we still did not actually have the elusive "building permit".

Yes, you read that correctly.

After all the applications, approvals, inspections, engineering, permits, fees, and thousands of dollars spent, I had somehow reached the stage of installing the deck foundations before discovering that the one permit I thought all of this was leading toward—the building permit itself—had still not been issued.

By this stage, our “minor deck project” was becoming a very good lesson in municipal bureaucracy.

I loved the fact that their machine went through our small gate.

Finally—The Building Permit

With the tree inspection finally complete, I went back to the City to apply for the building permit.

By this point, I had a few questions—and I could hardly believe I still had to ask them. I simply wanted to know, What exactly do I have to do now? After a number of conversations, I was eventually told to submit all of my documents to the appropriate person at the City. (No names here).

Of course, there was still one more issue to deal with. Because we had decided not to put a roof over the deck, the City initially wanted the drawings revised to reflect the change. After everything we had already gone through, the thought of having the drawings redone again was not particularly welcome. Fortunately, after some discussion, we managed to get that issue sorted out.

And finally—after the variance, the tree permit, the engineering certification, the screw piles, the inspections, the paperwork, and all the associated fees—we received our building permit. The City advised me that the next inspection would take place once all the main support beams, ledger boards, and related structural components were installed.

And that brings the story up to August 19, 2026.

The beams are going in, the deck is finally beginning to take shape, and—for the moment at least—we appear to have all the permits we need.

I hesitate to say that too loudly.

One More Wrinkle

Just to add another wrinkle to the project, when our contractor, Modest Fencing, arrived to begin the work, he noticed that all of the screw-pile supports had been fitted for 6 × 6 posts.

There was only one problem.

According to the approved drawings, three of the supports were supposed to accommodate 8 × 8 posts. And by this point, we had learned one lesson very well—the City expected the deck to be built according to the approved drawings-minus the roof!

The reason for the larger 8 × 8 posts was actually quite simple. Those particular supports had originally been designed to carry the weight of the roof we had planned for the deck. Of course, we were no longer building the roof, but the approved drawings still called for the larger posts.

So, once again, I picked up the phone.

I contacted Postech, explained the situation, and to their credit they responded immediately. They came over and replaced the three supports with the proper 8 × 8 versions.

Naturally, there was an additional charge—a few hundred dollars more. By now, that phrase had become almost as much a part of the project as lumber and screws.

With that problem solved, we are now waiting for the delivery of the 8 × 8 posts, Trex composite decking, and the rest of the materials needed to move ahead with construction.

And appropriately enough, all of it is scheduled to arrive on 20 August-Sharon’s birthday.

Nothing says “Happy Birthday” quite like a truckload of lumber and Trex arriving in the driveway.

Progress on the framing is being made. Modest is looking at a possible City inspection by late Monday morning.

21 August

22 and 23 August the project is on "pause" as we await the City inspector. Black tape on deck joists is joist tape, a self-adhering waterproof membrane applied to the top of framing members to block moisture, prevent fastener-hole rot, and extend substructure life.

24 August is the City inspection of the foundation which is scheduled for 2:30PM.

We passed the inspection

25 August. To begin, they we blowing the water off the joists. The process is back on track to finish next Friday!

We walked out on our deck earlier this evening once everyone was gone. One thing for sure, it is a big deck. It'll look smaller and with more character once the glass railings get inserted. Tomorrow is another day. Good work was done by all. Oh, they came back to put the black ice shield tape on the steps.

26 August

End of the day

31 August. Now the fascia and lets take a look underneath the deck. The opening to the right of the fascia is going to be the door to access underneath the deck.

Railings are going up but with the weather forecast calling for raining tomorrow which mean that the finishing stands may only go up on Wednesday. The glass inserts are only due in 2 weeks

End of day. Lots of work was done and cleaning up. It is supposed to rain tomorrow, let's hope not as they are scheduled to put on the railings on the north side and east side and then another half day to finish the stairs and insert the railings for the stairs. It's coming together.

1 September. Bones of the railings are done. Now they are working on the steps and the support railing going down. Oh ya, we will need to wait for the glass inserts before calling the City for a final inspection.

End of day. Now a few days break and they'll be back Saturday to do the railings of the stairs and the door access for underneath the deck...oh and also the water drain from the roof.

5 Sep. They are starting to work on the railings. After watching ( I told my lovely wife I was supervising lol), I can see why it is an art just to do that part.

They are finished for the day and will be back to install the glass on the deck railings, make a door for the fascia entrance and address the drain pipe that presently drains on our deck!

15 September. Back at it for the glass in the railings and the door to access underneath the deck

They went along and all the glass is in

The access is finished. JOB WELL DONE

Now we wait for the final inspection on Friday. I am sure it will go off without a problem. I do want to thank all those who participated and helped bring this project to its final conclusion.